Implement Phase Appendices
These appendices provide practical templates, checklists, registers, and implementation tools to support the five stages of the Implement Phase:
- Identify Critical Business Services
- Map Interconnections and Interdependencies
- Set Impact Tolerance
- Conduct Scenario Testing
- Improve Lessons Learned
The templates should be adapted to reflect the organisation’s size, complexity, regulatory environment, risk profile, governance structure, and operational resilience maturity.
Appendix D: Interconnections and Interdependencies Mapping Template
D.1 Critical Business Service
|
Field |
Details |
|
CBS Reference |
|
|
Critical Business Service |
|
|
Service Owner |
|
|
Mapping Owner |
|
|
Date Completed |
|
|
Last Review Date |
D.2 Dependency Mapping
|
Service Activity |
People |
Process |
Technology |
Facility |
Information |
Third Party |
|
Activity 1 |
||||||
|
Activity 2 |
||||||
|
Activity 3 |
||||||
|
Activity 4 |
D.3 Dependency Characteristics
For each dependency, identify:
- owner;
- location;
- recovery capability;
- availability of substitute;
- alternate capacity;
- upstream dependencies;
- downstream dependencies;
- shared services;
- external dependencies; and
- known vulnerabilities.
"Implement" Phase of the OR Planning Methodology
| Identify Critical Business Services |
Map Inter-connection and Inter-dependencies |
Set Impact Tolerance | Conduct Scenario Testing | Improve Lessons Learned | |
![]() |
![]() |
![]() |
![]() |
![]() |
More Information About Blended Learning OR-5000 [BL-OR-5] or OR-300 [BL-OR-3]
Contact our course consultant colleagues to learn more about our blended learning program and about the next course's schedule. They are the BL-OR-3 Blended Learning OR-300 Operational Resilience Implementer and the BL-OR-5 Blended Learning OR-5000 Operational Resilience Expert Implementer.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
|
![]() |
![]() |



![[OR] [PM] [P2] 5 Stage of Implement Phase](https://no-cache.hubspot.com/cta/default/3893111/936cc697-2dbe-4ede-a43d-f063ecdedf4b.png)


![[OR] [Banner] [How to] [P2] [S2] Map Interconnections and Interdependencies](https://no-cache.hubspot.com/cta/default/3893111/bde0890f-fc7e-4543-ac02-d32d78eaa9a2.png)

![[OR] [PM] [T] [P2] [TOC] Implement Phase Appendix](https://no-cache.hubspot.com/cta/default/3893111/e968fb12-bd2a-4501-afa0-7de4d0dbc8dc.png)










![[BL-OR] [3-4-5] View Schedule](https://no-cache.hubspot.com/cta/default/3893111/d0d733a1-16c0-4b68-a26d-adbfd4fc6069.png)
![[BL-OR] [3] FAQ OR-300](https://no-cache.hubspot.com/cta/default/3893111/f20c71b4-f5e8-4aa5-8056-c374ca33a091.png)
![Email to Sales Team [BCM Institute]](https://no-cache.hubspot.com/cta/default/3893111/3c53daeb-2836-4843-b0e0-645baee2ab9e.png)