PART B: CORPORATE CRISIS PROCEDURES
15. Sequential Flowchart
Pre-Crisis Preparation |
|
Crisis Occurs |
|
Immediate Response |
Site / DR Site / Command Centre – T + xx hours |
Recovery |
|
Resumption |
|
Restoration |
|
Return |
|
16. Overall Incident Response and Recovery Timeline
The timeline below should be revised to align with ABC's overall timeline for incident response and recovery operations.
17. Detailed Procedures
17.1. The following table shows the detailed procedures for each part of the flowchart shown in paragraph 1.
17.2. Tasks to be performed by the BUCs/ Alt BUCs are in bold.
Task Ref. |
Tasks |
Person Responsible |
Document |
Annex |
PRE-CRISIS (PREPARATION) |
||||
A01 |
Update the corporate and business unit Business Continuity (BC) Plan on an annual basis or upon significant changes. |
Org BCM Coordinator/ BUCs/ Alt. BUCs |
Corporate & BU BC Plan |
- |
A02 |
Store vital records at off-site storage facilities |
BUCs/ Alt. BUCs |
Vital Records |
Annex 7 |
A03 |
Agree on the vital records retrieval SLA with the off-site storage vendor |
Org BCM Coordinator |
SLA |
Annex 10 |
A04 |
Pre-arrange with vendors for the delivery of additional equipment to the Alternate Site / Command Centre during a crisis. |
Admin/ IT |
Alternate Site/ Command Centre Equipment List |
Annex 5 & 6 |
A05 |
Agree on the Alternate Site / Command Centre setup and support SLA with relevant parties. |
Org BCM Coordinator |
SLA |
Annex 10 |
A06 |
Familiarise business unit staff with the BU BC plan contents |
BUCs/ Alt. BUCs |
BU BC Plan |
- |
A07 |
Familiarise business unit staff with procedures for manual process, if any |
BUCs/ Alt. BUCs |
Manual Process Procedures |
Annex 9 |
A08 |
Verify and ensure that the facilities and equipment at the Alternate Site are sufficient to support business requirements. |
BUCs/ Alt. BUCs |
Alternate Site Equipment List |
Annex 5 |
A09 |
Check and ensure facilities and equipment in the Command Centre are operational. |
Org BCM Coordinator |
Command Centre Equipment List |
Annex 6 |
A10 |
Pre-arrange transportation for staff relocation during an emergency with relevant vendors (where necessary and applicable) |
Admin |
SLA |
Annex 10 |
CRISIS OCCURS | ||||
IMMEDIATE RESPONSE | ||||
|
During Office Hours |
|
|
|
B01 |
Evacuate all staff if needed |
Fire Wardens |
Fire Evacuation Plan |
|
B02 |
Remind staff during the evacuation to retrieve items under the 'Grab List' |
BUCs/ Alt. BUCs |
Grab List |
Annex 1 |
B03 |
Assemble at Primary Assembly Point <insert address>. If wet weather, evacuate to the Alternate Assembly Point <insert address> |
All staff |
Evacuation Assembly Points |
Part A – No. 6 |
B04 |
Check premises for full evacuation |
Fire Wardens |
- |
- |
B05 |
Conduct a roll call at the Assembly Point to ensure everyone is out of the building. |
Fire Wardens |
|
- |
B06 |
Activate Damage Assessment Team (DAT) |
Organisation BCM Coordinator / CMT Leader |
|
|
B07 |
Assess damage of premises by Damage Assessment Team (DAT) |
DAT |
Damage Assessment Checklist |
- |
B08 |
Activate Corporate Call Tree Notification to convene CMT |
Organisation BCM Coordinator / CMT Leader |
Corporate Call Tree |
Part A - No 7 |
B09 |
Declare a disaster and activate the Corporate BC Plan / Alternate Site |
Organisation BCM Coordinator / CMT Leader |
Corporate BC Plan |
Part A & B |
B10 |
Liaise with Corp Comm to release statements on crisis situation to key stakeholders, e.g. media, customers, shareholders, public, staff, etc., as necessary |
CMT |
|
|
B11 |
Activate Business Unit Call Tree notification and BC Plan, and advise the recovery team to arrive at the alternate site by <time> hour. |
BUCs/ Alt. BUCs |
BU Call Tree |
Annex 3 |
B12 |
Perform salvage and restoration if possible |
SRT |
Salvage & Restoration List |
Annex 2 |
B13 |
Arrange transfer/ storage/ treatment of salvaged items |
SRT |
|
|
B14 |
Review actions to be taken for repair/ renovation/restoration |
SRT |
|
|
B15 |
Report status to the Command Centre periodically |
BUCs/ Alt. BUCs |
Status Report |
Annex 4A |
|
Outside Office Hours |
|
|
|
BB01 |
Notify the Organisation BCM Coordinator when a crisis occurs at the primary office. |
Command Centre / Fire Command Centre |
- |
- |
BB02 |
Notify the Crisis Management Team (CMT) Leader of the crisis |
Organisation BCM Coordinator |
- |
- |
BB03 |
Activate Damage Assessment Team (DAT) |
Organisation BCM Coordinator / CMT Leader |
- |
- |
BB04 |
Assess the damage to the premises |
DAT |
Damage Assessment Checklist |
- |
BB05 |
Activate Corporate Call Tree Notification to convene CMT |
Organisation BCM Coordinator / CMT Leader |
Corporate Call Tree |
Part A - No 7 |
BB06 |
Declare a disaster and activate the Corporate BC Plan / Alternate Site |
Organisation BCM Coordinator / CMT Leader |
Corporate BC Plan |
Part A & B |
BB07 |
Liaise with Corp Comm to release statements on crisis situation to key stakeholders, e.g. media, customers, shareholders, public, staff, etc., as necessary |
CMT |
|
|
BB08 |
Activate Business Unit Call Notify the tree notification and BC Plan, and advise the recovery team to arrive at the alternate site by <time> hours. Non-recovery team to stay at home and await further instructions |
BUCs/ Alt. BUCs |
Business Unit Call Tree |
Annex 3 |
BB09 |
If staff arrive at the office and If they are denied access to the building, they will gather at Primary Assembly Point at <insert address>. If wet weather, gather at the Alternate Assembly Point at <insert address> and await instructions |
Individual staff members |
Evacuation Assembly Points |
Part A – No. 6 |
BB10 |
Activate the Business Unit BC Plan |
BUCs/Alt BUCs |
BU BC Plan |
Part C |
BB11 |
Perform salvage and restoration if possible |
SRT |
Salvage & Restoration List |
Annex 2 |
BB12 |
Arrange transfer/ storage/ treatment of salvaged items |
SRT |
|
|
BB13 |
Activate transportation arrangements with relevant vendors where necessary to relocate recovery teams to the alternate work locations. |
Organisation BCM Coordinator |
Corporate BC Plan |
Part A & B |
BB14 |
Review actions to be taken for repair/ renovation/restoration |
SRT |
|
|
BB15 |
Report status to the Command Centre periodically |
BUCs/Alt BUCs |
Status Report |
Annex 4A |
RECOVERY AND RESUMPTION | ||||
C01 |
Advise the phone company to route office phone lines to the alternate site |
Admin / IT |
|
|
C02 |
Display a notice at the primary office giving directions to the Alternate Site. |
Admin |
|
|
C03 |
Coordinate any necessary transportation requirements if needed |
Admin |
|
|
C04 |
Arrange mail routing with courier/mail services to the alternate site |
Admin |
|
|
C05 |
The recovery team occupy the Alternate Site |
BUCs/Alt BUCs |
Alternate Site Address |
Part A – No. 5 |
C06 |
CMT occupy the Command Centre and is ready to operate |
CMT / IT |
|
Part A – No. 5 |
C07 |
Verify that all facilities, equipment, and materials are available at the Alternate Site. |
BUCs/Alt BUCs |
Facilities, Equipment and Materials Inventory |
Annex 5 |
C08 |
Activate delivery of equipment to the Alternate Site if needed |
IT / Admin Team |
Equipment Inventory & Vendor Contact List |
- |
C09 |
Re-input backlogged, lost transactions and manual data |
BUCs/Alt BUCs |
|
|
C10 |
Notify all business partners, customers and suppliers of the relocation of business operations. |
BUCs/Alt BUCs |
Key Contact List |
Annex 8 |
C11 |
Liaise with Corp Comm to release statements on crisis situation to key stakeholders, e.g. media, customers, shareholders, public, staff, etc., as necessary |
CMT |
|
|
C12 |
Report status to the Command Centre periodically |
BUCs/Alt BUCs |
Status Report |
Annex 3B or 3C |
RESTORATION AND RETURN |
||||
D01 |
Restore the primary office to ensure facilities, office and IT equipment are operational once CMT decides on restoration. |
Admin / Facilities / IT |
- |
- |
D02 |
Brief BUCs to restore normal operations |
Organisation BCM Coordinator |
- |
- |
D03 |
Verify that the primary office, facilities, and materials are ready and operational. |
BUCs/Alt BUCs |
|
|
E04 |
Implement system restoration and data synchronisation procedures |
IT Team |
IT DRP |
- |
E05 |
Verify that all recovery data has been successfully loaded back to production systems. |
BUCs/Alt BUCs |
- |
- |
E06 |
Advise the phone company to route office phone lines to the alternate site |
Admin / IT |
|
|
E07 |
Advise all staff to return to the primary office |
BUCs/Alt BUCs |
|
|
E08 |
Restore business functions in the primary office in batches and ensure a parallel run on both the primary and backup sites for a period of 7 days before completing a fallback to the normal mode of operations. |
Org BCM Coordinator/ BUCs/ Alt BUCs |
|
|
E09 |
Report status to the Command Centre periodically |
BUCs/Alt BUCs |
Status Report |
Annex 3D |
E10 |
Re-commence the normal mode of operations |
BUCs/Alt BUCs |
- |
- |
E11 |
Announce the closure of the alternate site and stand down the CMT. |
CMT Leader / Org BCM Coordinator |
|
|
E12 |
Liaise with Corp Comm to release statements on crisis to key stakeholders, e.g. media, customers, shareholders, public, staff, etc., as necessary |
CMT |
|
|
E13 |
Notify all business partners, customers and suppliers of a return to normal operations. |
BUCs/Alt BUCs |
Key Contact List |
Annex 8 |
18. Distribution and Approval
18.2 This plan is to be distributed as follows:- All Business Unit BCM Coordinators
- All Alternate Business Unit BCM Coordinators
- All Business Unit Heads
- All Crisis Management Team Members
- Primary and Alternate Organisation BCM Coordinators
Note: All plan holders must discard all obsolete copies upon receipt of the latest version.
SIGNOFF
Plan Updated By: |
________________________________________ <insert full name here> (Name of Organisation BCM Coordinator) |
Date: | |
Plan Approved By: |
________________________________________ <insert full name here> (Name of Organisation Head) |
Date: |
|