Full Simulation activates the total business continuity plan.  The purpose is to simultaneously test as many components as possible in the organization recovery structure.  An example of a Full Simulation is the Full Re-Location Test of the entire business. This template is a checklist for designing the test profile
Dr Lim Yew Ban
Business Continuity Management Certified Planner-Specialist-Expert

Testing Business Continuity Exercises

Table of Content [1] for BCM Testing and ExercisingThis is a series of useful templates that you can use to develop the  Testing and Exercising program.

IC_TE_DesignProfile_FullSimulation

Design Profile for Full Simulation

Explanation

Full Simulation activates the total business continuity plan.  The purpose is to simultaneously test as many components as possible in the organization recovery structure.  An example of a Full Simulation is the Full Re-Location Test of the entire business. This template is a checklist for designing the test profile.

 

Definition

 
Objective Confirm ALL aspects of the invocation of the alternate (recovery) site for KEY business units from a particular location
Scope and Scale (Active/ Passive; degree of involvement) Active.  All support group teams and one or more key business unit teams
Components to be tested  
Plans  Yes
People Yes
Place Yes
Resources Yes
Success Criteria All aspects of support and business, planned for testing, were tested
Essential Pre-Conditions The plans for all units (both business and support) must have previously been tested at every subordinate level
Participants   
Internal Yes
External Yes

Scheduling

 
Time of Test/Schedule Always out of business hours, on a weekend/public holiday (to avoid disruption of normal business activities)
Duration Maximum 2 Days (to allow support group call out and set-up prior to business unit involvement plus re-instatement)
Frequency (mandatory/desirable) For critical business units maximum 1 year from the date of the last partial re-location test (mandatory).  After the first full re-location, tests should be carried out annually alternating between partial and full re-location tests.  To be scheduled with the full agreement of officer with governance responsibility for the territory
Notice Requirement/Warning Yes
Briefing of Participants A full briefing document should be prepared
Scenario No
Test of plan Yes
Budget for test Yes (overtime, transport, subsistence and recovery resource/invocation costs, outsourcing contract additional costs)

Execution/ Monitoring

 
Controllers

BCC

Document

 
Documentation (capable of audit) -Track events and degree of success

List of events with individual details and timings, controllers’/business unit document checklist. Business Unit log sheets, post test critique forms

Review/ Measure

 
Post-Mortem Meeting

Yes - immediate de-brief  plus a more formal review meeting some days later

Report/ Output

 
Post-Test Actions (documented) –link to maintenance/reporting

Record the outcome on the standard assessment pro-forma and document remedial actions required (with responsibilities and target dates)

Maintenance/ Follow-Up

Make amendments to plan as required

If appropriate, amend the plan(s). Where their remedial action requirement negates earlier test result(s), arrange appropriate re-test(s)

Testing & Exercising Your Business Continuity Plan (Second Edition)

 
Source

Goh, M. H. (2006). Testing and Exercising Your Business Continuity Plan. Business Continuity Management Series (2nd ed.). Singapore: GMH Pte Ltd.

Extracted from "Chapter 29: T7: Design Profile for Full Simulation"

More Information About Blended Learning BCM-5000 [BL-B-5]

To know more about our blended learning program and when the next course is scheduled, feel free to contact our friendly course consultant colleagues via sales.ap@bcm-institute.org.  They are the BL-B-3 Blended Learning BCM-300 ISO22301 BCMS Implementer and the BL-B-5 Blended Learning BCM-5000 ISO22301 BCMS Expert Implementer.

New call-to-action New call-to-action New call-to-action
New call-to-action New call-to-action New call-to-action
  FAQ [BL-B-3]

Please feel free to send us a note if you have any of these questions to sales.ap@bcm-institute.org

 FAQ BL-B-5 BCM-5000  
 

  

For Your Comments

More Posts

New Call-to-action