Introduction
A hospital must decide what it will do about each risk, and how much risk remains afterwards. This chapter sets out the proposed mitigation strategies for Eastern General Hospital (EGH), building on the threats in Chapter 3, the controls in Chapter 4 and the ratings in Chapter 5.
The strategies support business continuity management (BCM) strategy selection under clause 8.3 of ISO 22301. They are proposals for approval by senior management. The ratings and controls are illustrative, and every existing control is assumed and requires validation. Targets keep the impact score of Chapter 5 and change only the likelihood, because controls usually act on how often a threat occurs rather than how severe the outcome would be.
How Strategies Were Chosen
- Reduce: 24 threats have a reduction strategy, mostly High ratings.
- Transfer: 6 threats include transfer through insurance or contract terms.
- Accept and monitor: 7 threats are accepted with monitoring, because their ratings are Moderate and the cost of further control is not justified.
Each strategy names a specific action, so that an owner can plan it. The justification explains why that action is proportionate to the rating.
Mitigation Strategies
Table BCS P1: Mitigation Strategies for Eastern General Hospital
| Threat | Existing Controls (assumed, requires validation) | Risk Rating | Risk Level | Risk Treatment (Residual Risk) | Additional Mitigation Strategy | Justification for Selected Mitigation Strategy |
|---|---|---|---|---|---|---|
| Flash Flood | Site drainage and flood levels designed for the campus (Preventive); Weather alerts monitored by facilities (Detective) | 6 | Moderate | Reduce; target rating 3 (Very Low / Low) | Pre-agreed ambulance diversion routes and stockpiled flood barriers | Low cost, and it protects the emergency access route. |
| Severe Thunderstorm and Lightning | Lightning protection and surge protection (Preventive); Uninterruptible power for critical loads (Compensating) | 9 | Moderate | Accept and monitor; target rating 9 (Moderate) | Routine testing and storm checklist | Impact is manageable with existing protection; effort is better spent elsewhere. |
| Extreme Heat | Chiller capacity with redundancy (Preventive); Heat advisory to staff (Directive) | 9 | Moderate | Accept and monitor; target rating 9 (Moderate) | Heat protocol for wards and outdoor staff | Existing cooling is adequate for expected conditions. |
| Transboundary Haze | Air filtration on fresh-air intake (Preventive); Air quality monitoring (Detective) | 6 | Moderate | Accept and monitor; target rating 6 (Moderate) | Mask stock and a surge plan for respiratory cases | Predictable and slow-moving; existing controls suffice. |
| Pandemic-Related Movement Restrictions | Infectious disease preparedness plan (Directive); Isolation capacity in design (Preventive) | 10 | High | Reduce; target rating 5 (Moderate) | Surge and cohorting plan, stockpile rotation and exercise | Severe consequences justify investment despite low likelihood. |
| Distant Earthquake Tremors | Structural design to local standards (Preventive); Tremor response guide (Directive) | 6 | Moderate | Accept and monitor; target rating 6 (Moderate) | Inspection procedure and staff briefing | Rare and low impact. |
| Fire | Fire detection, sprinklers and compartmentation (Preventive); Fire wardens and evacuation plan (Corrective) | 10 | High | Reduce and transfer; target rating 5 (Moderate) | Exercise horizontal and vertical evacuation; confirm property insurance | Patient safety makes this a priority despite low frequency. |
| Bomb Threat | Bag and visitor screening policy (Preventive); Bomb threat procedure (Directive) | 8 | Moderate | Reduce impact and accept residual likelihood; target rating 8 (Moderate) | Exercise with police and clinical relocation | Moderate rating, but reputational and safety effects justify low-cost exercises. |
| Active Assailant | Access control and CCTV (Preventive); Lockdown protocol (Corrective) | 5 | Moderate | Reduce impact and accept residual likelihood; target rating 5 (Moderate) | Regular joint exercises with the police | Very low likelihood; keep as monitored risk with training. |
| Chemical or Gas Leak | Chemical storage controls and gas alarms (Preventive); Spill response kits (Corrective) | 8 | Moderate | Reduce impact and accept residual likelihood; target rating 8 (Moderate) | Spill drills and gas-detection tests | Controls are adequate when exercised. |
| Structural or Building Services Failure | Planned preventive maintenance (Preventive); Engineering inspections (Detective) | 5 | Moderate | Reduce impact and accept residual likelihood; target rating 5 (Moderate) | Alternate ward capacity map | Very low likelihood; monitor. |
| Major Road or Public Transport Disruption | Shuttle and shift handover rules (Compensating); Traffic updates to staff (Detective) | 9 | Moderate | Accept and monitor; target rating 9 (Moderate) | Staff travel alerts and shuttle | Impact is short-lived. |
| Infectious Disease Outbreak | Infection control policy and isolation rooms (Preventive); Surveillance by infection control team (Detective) | 15 | High | Reduce; target rating 10 (High) | Outbreak exercise and staffing surge pool | Patient safety and regulator interest. |
| Mass Staff Illness | Cross-trained staff roster (Compensating); Staff health screening (Preventive) | 10 | High | Reduce impact and accept residual likelihood; target rating 10 (High) | Staffing matrix and reserve pool | Moderate-high rating warrants simple preparation. |
| Loss of Key Clinical Personnel | Succession planning (Preventive); Locum agreements (Compensating) | 12 | High | Reduce; target rating 8 (Moderate) | Key-person cover list and locum framework | Moderate disruption but credible likelihood. |
| Healthcare Manpower Shortage | Recruitment pipeline (Preventive); Overtime rules (Directive) | 16 | High | Reduce; target rating 12 (High) | Phased ramp-up and retention measures | Highest-probability people risk during opening. |
| Workplace Violence | Security presence in emergency areas (Preventive); Incident reporting (Detective) | 12 | High | Reduce; target rating 8 (Moderate) | Training and alarm coverage | Frequent, so worth reducing. |
| Staff Fatigue and Burnout | Rostering rules (Directive); Staff support service (Corrective) | 16 | High | Reduce; target rating 12 (High) | Rostering and wellbeing programme | Persistent condition. |
| Critical Medical Supplier Failure | Approved supplier list (Preventive); Safety stock levels (Compensating) | 12 | High | Reduce and transfer; target rating 8 (Moderate) | Dual sourcing and contract continuity clauses | Reduces single-point dependency. |
| Pharmaceutical Stock-out | Medicine stock monitoring (Detective); Therapeutic substitution protocol (Compensating) | 15 | High | Reduce; target rating 10 (High) | Critical medicine list with buffer and alternates | Direct patient harm potential. |
| Cloud Service Provider Failure | Service level agreement with provider (Directive); Offline downtime procedures (Compensating) | 10 | High | Reduce and transfer; target rating 5 (Moderate) | Failover design and contractual recovery targets | Technology dependency is rising. |
| Telecommunications Provider Failure | Diverse carrier links (Preventive); Radio back-up (Compensating) | 8 | Moderate | Accept and monitor; target rating 8 (Moderate) | Carrier diversity check | Existing diversity adequate. |
| Water Supply Failure | On-site water storage (Compensating); Utility contact list (Directive) | 5 | Moderate | Accept and monitor; target rating 5 (Moderate) | Tanker agreement | Low likelihood. |
| Outsourced Service Provider Failure | Contract service levels (Directive); Alternate contractor list (Compensating) | 9 | Moderate | Reduce and transfer; target rating 6 (Moderate) | Contractor continuity requirements | Common and manageable. |
| Ransomware Attack | Endpoint protection and email filtering (Preventive); Offline backups (Corrective) | 15 | High | Reduce and transfer; target rating 10 (High) | Immutable backups and cyber exercise; confirm cyber insurance | Highest consequence technology threat. |
| Power Failure | Standby generators and uninterruptible power (Compensating); Power monitoring (Detective) | 10 | High | Reduce; target rating 5 (Moderate) | Regular on-load tests and fuel supply contract | Power is fundamental to patient life support. |
| Electronic Medical Record System Failure | System redundancy (Preventive); Downtime forms (Compensating) | 15 | High | Reduce; target rating 10 (High) | Downtime drills and read-only replica | Frequent dependence. |
| Medical Equipment Failure | Maintenance contracts (Preventive); Spare equipment pool (Compensating) | 12 | High | Reduce; target rating 8 (Moderate) | Loaner agreements and spares | Moderately frequent. |
| Network and Data Centre Outage | Redundant core network (Preventive); Secondary data hall (Compensating) | 10 | High | Reduce; target rating 5 (Moderate) | Failover tests | Single point of failure for many functions. |
| Air-Conditioning and Ventilation Failure | Redundant chillers (Preventive); Temperature alarms (Detective) | 8 | Moderate | Reduce; target rating 4 (Very Low / Low) | Spot cooling plan | Theatres rely on ventilation. |
| Data Breach or Insider Misuse | Role-based access and logging (Preventive); Staff privacy training (Directive) | 15 | High | Reduce and transfer; target rating 10 (High) | Access review, monitoring and breach notification drill | Regulatory and reputational exposure. |
What the Targets Mean
Of the 17 High threats, 9 fall below High if the strategies work as planned. The other 8 remain High at target: Infectious Disease Outbreak, Mass Staff Illness, Healthcare Manpower Shortage, Staff Fatigue and Burnout, Pharmaceutical Stock-out, Ransomware Attack, Electronic Medical Record System Failure, Data Breach or Insider Misuse. For these, further treatment or a formal risk acceptance by senior management is needed, because the hospital cannot reduce them further with the actions in the table alone.
Implementation Roadmap
The roadmap groups the strategies by timeframe using the priorities from Chapter 4. Owners are the lead owners only; supporting teams are agreed during planning.
Table BCS P1-R: Implementation Roadmap for Eastern General Hospital (lead owners)
| Timeframe | Priority | Number of Threats | Threats | Lead Owners |
|---|---|---|---|---|
| 0–6 months | Priority 1 | 7 | Infectious Disease Outbreak, Healthcare Manpower Shortage, Staff Fatigue and Burnout, Pharmaceutical Stock-out, Ransomware Attack, Electronic Medical Record System Failure, Data Breach or Insider Misuse | Chief Information Officer; Chief Information Security Officer; Chief Pharmacist; Director, Human Resources; Head, Infection Prevention and Control |
| 6–12 months | Priority 2 | 10 | Pandemic-Related Movement Restrictions, Fire, Mass Staff Illness, Loss of Key Clinical Personnel, Workplace Violence, Critical Medical Supplier Failure, Cloud Service Provider Failure, Power Failure, Medical Equipment Failure, Network and Data Centre Outage | Chief Information Officer; Chief Medical Officer; Director, Facilities and Engineering; Director, Human Resources; Head, Biomedical Engineering; Head, Infection Prevention and Control; Head, Procurement; Head, Security |
| 12–24 months | Priority 3 | 14 | Flash Flood, Severe Thunderstorm and Lightning, Extreme Heat, Transboundary Haze, Distant Earthquake Tremors, Bomb Threat, Active Assailant, Chemical or Gas Leak, Structural or Building Services Failure, Major Road or Public Transport Disruption, Telecommunications Provider Failure, Water Supply Failure, Outsourced Service Provider Failure, Air-Conditioning and Ventilation Failure | Chief Information Officer; Chief Nurse; Director, Facilities and Engineering; Head, Procurement; Head, Security |
Next Steps for the Hospital
- Validate: owners confirm existing controls and evidence listed in Chapter 4.
- Approve: senior management approves the strategies, the targets and any risk acceptance.
- Plan: each owner converts the strategy into a funded action with a date.
- Exercise: the hospital tests the strategies before opening and updates the ratings.
- Review: the business continuity steering group reviews progress at least every quarter.
Conclusion
The mitigation strategies show how EGH plans to move its risk profile towards an acceptable level, and where management must still decide. They do not mean that controls are already in place: each one is a plan awaiting validation, funding and testing.
With the minimum objectives, the services they protect, the threats and the strategies defined, the hospital has the core inputs for its continuity plans.
Continue reading: explore BCM Institute's ISO 22301 courses and certifications at blog.bcm-institute.org/certification, and learn how to turn these strategies into tested continuity plans.