[BCM] [EGH] [E1] [C8] Implementing the BCM Planning Methodology for Eastern General Hospital

New call-to-action

Eastern General Hospital (EGH) needs more than good intentions to become resilient. It needs a method that takes the programme from a first meeting to plans that have been tested and kept current.

A planning methodology provides that route, and it lets leaders see what has been done, what is under way and what is still to come.

Chapter 7 analysed EGH's operating environment. This chapter describes a seven-phase planning methodology: Project Management (PM), Risk Analysis and Review (RAR), Business Impact Analysis (BIA), Business Continuity Strategy (BCS), Plan Development (PD), Testing and Exercising (TE) and Program Management (PgM). These phases map to clauses 4.3, 4.4, 8.1 to 8.5, 9, and 10 of ISO 22301:2019.

Singapore has no national BCM policy for hospitals, so this method follows the standard and the Ministry of Health (MOH) licensing expectations, with unconfirmed requirements marked.

Moh Heng Goh

New call-to-action

New call-to-action

Introduction

Eastern General Hospital (EGH) needs more than good intentions to become resilient. It needs a method that takes the programme from a first meeting to plans that have been tested and kept current.

A planning methodology provides that route, and it lets leaders see what has been done, what is under way and what is still to come.

Chapter 7 analysed EGH's operating environment. This chapter describes a seven-phase planning methodology: Project Management (PM), Risk Analysis and Review (RAR), Business Impact Analysis (BIA), Business Continuity Strategy (BCS), Plan Development (PD), Testing and Exercising (TE) and Program Management (PgM). These phases map to clauses 4.3, 4.4, 8.1 to 8.5, 9, and 10 of ISO 22301:2019. Singapore has no national BCM policy for hospitals, so the method follows the standard and the licensing expectations of the Ministry of Health (MOH), with unconfirmed requirements marked [verify].

Scope of the Management System

Clauses 4.3 and 4.4 ask EGH to define the scope of its business continuity management system (BCMS). For EGH, the scope might cover virtual and home-based services now, the hospital and its support functions as each phase opens, and the interfaces with Eastern Community Hospital (ECH) and SingHealth shared services. Exclusions must be stated and justified.

A scope that grows with the campus is more realistic than one that tries to cover the finished hospital on day one. EGH might publish a roadmap showing which services enter the BCMS at which phase.

Phase 1: Project Management

The first phase sets up the programme. It confirms the sponsor, appoints the BCM coordinator, agrees scope, budget and timetable, and establishes the steering committee described in Chapter 6. EGH might also create a programme plan that aligns with the construction and commissioning milestones, so that continuity work happens before design and service decisions are fixed.

Phase 2: Risk Analysis and Review

This phase identifies threats to prioritised activities and the resources they rely on, assesses likelihood and impact, and decides which risks need treatment. It corresponds to clause 8.2.3 and draws on ISO 31000:2018 for the wider risk language. Chapter 9 covers it in depth. For example, EGH might review the risk of a prolonged power failure for its operating theatres and the effect of cyber-attacks on its clinical systems.

Phase 3: Business Impact Analysis

The BIA identifies the activities that matter most and the effect of losing them over time. It sets the maximum tolerable period of disruption (MTPD), the recovery time objective (RTO) and the minimum business continuity objective (MBCO) for each prioritised activity, and it lists the resources required. This is clause 8.2.2. Chapter 10 introduces the critical business functions that the BIA will confirm.

BIA workshops work best with clinicians in the room. EGH might ask a clinical lead and a nurse manager from each major service to estimate how long a service can be interrupted before patients are harmed, and then challenge those estimates against evidence.

Phase 4: Business Continuity Strategy

Strategy selection, under clause 8.3, decides how EGH will protect and recover each prioritised activity. Options include resilience built into the design, alternative locations or capacity within SingHealth, manual workarounds, reserve stocks, alternative suppliers, and insurance or transfer arrangements. A strategy should be justified by the BIA and the risk assessment, and it should be affordable.

For example, EGH might choose to protect its electronic records with a secondary data path and tested downtime procedures, and to protect its pharmacy with agreed minimum stock levels and an alternative supplier.

Phase 5: Plan Development

Plan development turns strategies into usable documents, under clause 8.4. Typical plans include an incident management plan, department continuity plans, a crisis communication plan, an information technology disaster recovery plan, a pandemic or outbreak plan, and a facilities failure plan. Plans should be short, role-based and written for use under stress.

Each plan names its trigger, the people who activate it, the first actions, the resources needed and the criteria for standing down.

Phase 6: Testing and Exercising

Plans that have not been exercised should not be trusted. Clause 8.5 expects an exercise programme with defined aims, realistic scenarios and recorded outcomes. EGH might begin with walk-throughs and table-top discussions, then move to functional exercises with clinical teams, and later to full simulations that include SingHealth and external agencies.

Every exercise should end with a debrief and a list of actions with owners and dates.

Phase 7: Program Management

Program management keeps the BCMS alive. It covers training and awareness (clauses 7.2 and 7.3), document control (7.5), monitoring and internal audit (9.1 and 9.2), management review (9.3) and continual improvement (10). It also includes change management, so that new services, systems and buildings enter the BCMS as they come online.

For EGH, this phase matters in a particular way. The campus will change repeatedly as it opens, and every change can invalidate earlier assumptions. A change process that asks whether a new service, supplier or system alters continuity needs will prevent gaps.

Applying the Method across the Campus Phases

The seven phases do not run once. For EGH, they repeat for every service that joins the BCMS. A practical pattern is to run a first full cycle for the services that exist now, namely virtual and home-based care, then to run a lighter cycle for each campus phase as its design firms up.

The first cycle builds the foundations: the steering committee, the risk method, the BIA template and the plan format. Later cycles reuse these, so departments in the second and third phases find the work easier. A lessons-learned review at the end of each cycle improves the templates.

The programme should also link to the construction and commissioning calendar. For instance, the BIA for a major theatre complex should finish before the design of its power, ventilation and medical gas systems is fixed. Plans and exercises should finish before go-live, with a readiness review that includes the BCM coordinator.

Documents and Governance

Clause 7.5 expects documented information to be controlled. EGH might keep a small set of core documents: the policy, scope statement, risk method, BIA template, strategy summaries, incident plan and department plans, and exercise reports. Each should have an owner, a version number, an approval date and a review date.

Governance should be light but regular. The steering committee reviews progress each quarter, the governing body receives an annual report, and internal audit reviews the BCMS on a planned cycle. This pattern matches clauses 9.2 and 9.3, and it fits the way hospitals already manage clinical governance and risk.

Summary Table

Table 8: Implementing the BCM Planning Methodology for Eastern General Hospital

Phase Purpose Key outputs ISO 22301 clause Example at EGH
1. Project Management (PM) Set up the programme Scope, plan, steering committee 4.3; 4.4; 5.3 Programme timeline aligned with construction milestones
2. Risk Analysis and Review (RAR) Find and rate threats Risk register 6.1; 8.2.3 Power failure and cyber-attack scenarios
3. Business Impact Analysis (BIA) Identify priorities and targets Prioritised activities, MTPD, RTO, MBCO 8.2.2 Emergency department and theatre priorities
4. Business Continuity Strategy (BCS) Choose protection and recovery options Approved strategies 8.3 Downtime procedures and minimum stocks
5. Plan Development (PD) Write usable plans Incident and department plans 8.4 Outbreak and facilities failure plans
6. Testing and Exercising (TE) Prove the plans Exercise programme and reports 8.5 Downtime exercise with clinical teams
7. Program Management (PgM) Sustain and improve Training, audit, management review 7; 9; 10 Change control for each campus phase

Conclusion

A seven-phase method gives EGH a clear path from setting up the programme to sustaining it. The phases also fit the pace of a phased opening, since each new service can pass through risk analysis, BIA, strategy, plan development and exercising before it goes live. EGH should record scope and exclusions plainly and keep the method simple enough for busy clinical teams to follow.

The next chapter starts the detailed analysis by assessing the risks and threats that EGH faces.

Continue reading: Chapter 9, Assessing Risks and Threats for Eastern General Hospital, shows how EGH can identify, rate and treat the risks of disruption to its most important activities.

 

Keeping Care Running: Managing and Implementing Business Continuity Management at Eastern General Hospital
eBook 1: Understanding Your Organisation
C1 C2 C3 C4 C5 C6
[BCM] [EGH] [E1] [C1] Overview of BCM Case Study [BCM] [EGH] [E1] [C2] Understanding Your Organisation [BCM] [EGH] [E1] [C3] Establishing Organisational Goals [BCM] [EGH] [E1] [C4] Establishing Business Continuity Objectives [BCM] [EGH] [E1] [C5] Determining BC Assumptions [BCM] [EGH] [E1] [C6] Composing BCM Team
C7 C8 C9 C10 C11 C12
[BCM] [EGH] [E1] [C7] Analysing Operating Environment [BCM] [EGH] [E1] [C8] Implementing the BCM Planning Methodology [BCM] [EGH] [E1] [C9] Assessing Risks and Threats [BCM] [EGH] [E1] [C10] Identifying Critical Business Functions [BCM] [EGH] [E1] [C11] Summary [BCM] [EGH] [E1] [C12] Back Cover
 

Comments

CTA Banner_OR

CTA Banner_ORA

CTA Banner_BCM

CTA Banner_ITDR

CTA Banner_CM