From the table obtained in the previous BIA page Part [B], select any 3 functions that can be delayed. Discuss the rationale that they could be deferred.
|
For each shortlisted CBF in Part [B] state the minimum resource required. For example in terms of staff, facility/ admin support required (telephones, network connectivity, PCs, work area, etc.)
Business functions | Function Number | Brief Description | MTD/ RTO | Staff | No of Tels | No of PCs |
Admin | AD001 | Supply stationery & pre-printed Items – this includes stationery Items, pre-printed forms, documents, brochures, etc. | ||||
AD002 | Facility management – maintenance of system and equipment for building | |||||
AD003 | Support and management of telecommunications at HQs, branches and external offices | |||||
AD004 | Supply of office equipment and furniture |
Suggest probable broad objectives and steps that the organization IT function should embark upon to support BC
|
In terms of business function inter-dependency, identify specific functions which
|
What do you foresee to be the potential issues and difficulties that would be encountered in undertaking the above BIA activities ? Suggest resolutions to pre-empt or minimize these issues and difficulties.
|