Using the case study scenario given, perform a Business Impact Analysis (BIA) via the walk through of the steps.
Provide some key principles underlying the execution of this phase of BCM. For each principle discuss the reasons for its inclusion.
|
For the business functions provided in the case organization, tabulate the probable Recovery Time Objective or RTO. You may include in additional business functions as you deem fit.
|
Sample of function number and description of the business unit's functions.
Business functions | Function Number | Brief Description | RTO |
Admin | AD001 | Supply stationery & pre-printed Items – this includes stationery Items, pre-printed forms, documents, brochures, etc. | |
AD002 | Facility management – maintenance of system and equipment for building | ||
AD003 | Support and management of telecommunications at HQs, branches and external offices | ||
AD004 | Supply of office equipment and furniture |
Is the Maximum Tolerable Period of Disruption (MTPD) equal to the Recovery Time Objective (RTO) ?
|
What is the different between operational and BC requirements ? Are they the same ?
|