title: "[CM] [JHA] [E3] [CORE] Chapter 5: Treatment and Control for Jamiyah Home for the Aged"
description: How Jamiyah Home for the Aged can avoid, reduce, transfer or accept 22 threats, with existing and planned controls set out in one treatment and control table.
image: https://blog.bcm-institute.org/hubfs/JHA%20Graphic%20Folder/JHA%20CM%20Morepost/JHA%20CM%20E3%20Morepost/%5BCM%5D%20%5BJHA%5D%20%5BE3%5D%20%5BC4%5D%20%5BCRA%5D%20%5B1-3%5D%20Treatment%20and%20Control.png
---

.

[![BCMIWhiteLogo.png](https://blog.bcm-institute.org/hs-fs/hubfs/Blog%20Testing/BCMIWhiteLogo.png?width=556&name=BCMIWhiteLogo.png "BCMIWhiteLogo.png")](http://www.bcm-institute.org/)

- [Home](https://www.bcm-institute.org/)
- [About Us](https://www.bcm-institute.org/about-us-3/) 
    - [A President’s Perspective](https://www.bcm-institute.org/about-us/a-presidents-perspective/)
    - [Our History](https://www.bcm-institute.org/about-us/our-history/)
    - [Our Advisory Council](https://www.bcm-institute.org/about-us/our-advisory-council/)
    - [Customers’ Testimonials](https://www.bcm-institute.org/about-us/customers-testimonials/)
    - [Credential Verification](https://www.bcm-institute.org/about-us/credential-verification/)
- [Courses](https://blog.bcm-institute.org/blog/course-fees-for-blended-learning-courses-master-catalog) 
    - [ISO 22301 Business Continuity Management System Audit](https://blog.bcm-institute.org/audit/business-continuity-management-audit-courses)
    - [ISO 22301 Business Continuity Management](https://blog.bcm-institute.org/bcm/business-continuity-management-courses)
    - [Crisis Communication](https://blog.bcm-institute.org/crisis-communication/crisis-communication-courses)
    - [Crisis Management](https://blog.bcm-institute.org/en/crisis-management/courses)
    - [IT Disaster Recovery](https://blog.bcm-institute.org/it-disaster-recovery/courses)
    - [Operational Resilience](https://blog.bcm-institute.org/operational-resilience/courses)
    - [Operational Resilience Audit](https://blog.bcm-institute.org/operational-resilience-audit/courses)
- [Certification](https://blog.bcm-institute.org/certification/types-of-certifications-offered) 
    - [ISO 22301 BCMS Audit Certification](https://blog.bcm-institute.org/certification/business-continuity-management-audit-certification)
    - [ISO22301 Business Continuity Management Certification](https://blog.bcm-institute.org/bcm/business-continuity-management-certification)
    - [Crisis Communication Certification](https://blog.bcm-institute.org/crisis-communication/crisis-communication-certification)
    - [Crisis Management Certification](https://blog.bcm-institute.org/en/crisis-management/crisis-management-certification)
    - [IT Disaster Recovery Planning Certification](https://blog.bcm-institute.org/it-disaster-recovery/it-disaster-recovery-certification)
    - [Operational Resilience Certification](https://blog.bcm-institute.org/operational-resilience/operational-resilience-certification)
    - [Operational Resilience Audit Certification](https://blog.bcm-institute.org/operational-resilience-audit)
- [Seminars](https://blog.bcm-institute.org/meet-the-expert/mte-webinar-mainpage)
- [Store](https://www.bcm-institute.org/store-2/)
- [Contact Us](http://www.bcm-institute.org/about-us/contact-us/)

- <https://www.facebook.com/BCMInstitute/>
- <https://www.linkedin.com/company/business-continuity-management-institute-bcm-institute>

###### Crisis Management in Action: A Practical Implementation Guide for Jamiyah Home for the Aged

![JHA\_CM\_05\_Crisis\_Risk\_Impact\_and\_Likelihood](https://blog.bcm-institute.org/hs-fs/hubfs/JHA%20Graphic%20Folder/JHA%20BB%20Photo/JHA_CM_05_Crisis_Risk_Impact_and_Likelihood.png?width=2000&height=1333&name=JHA_CM_05_Crisis_Risk_Impact_and_Likelihood.png "JHA_CM_05_Crisis_Risk_Impact_and_Likelihood")

# \[CM\] \[JHA\] \[E3\] \[CORE\] Chapter 5: Treatment and Control for Jamiyah Home for the Aged

[![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/8ed24986-bf49-4aa4-865f-0c93142fa991.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/8ed24986-bf49-4aa4-865f-0c93142fa991)

[![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/422eee8a-7fb9-446e-8f52-c29f5ebcf795.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/422eee8a-7fb9-446e-8f52-c29f5ebcf795)Once the threats are listed, the next question is what Jamiyah Home for the Aged (JHA) already does about each one, and what more it should do. This chapter, Crisis Scenario Risk Assessment (CRA) Part 2, records the treatment and control for every threat from Chapters 2 and 4.

It covers all 22 threats. For each one, it shows the four treatment options, the controls believed to exist, and the controls planned.

*Every rating, control, strategy, and time target in this chapter is a proposed draft built from public information about JHA and must be validated by JHA before use.*

*[![\[CM\] \[E3\] \[C1\] Starting Your CM Implementation Banner](https://no-cache.hubspot.com/cta/default/3893111/1bf08c12-b11b-44cc-a7a5-3bd25c740d4c.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/1bf08c12-b11b-44cc-a7a5-3bd25c740d4c)*

*[![\[Logo\] \[CM\] Certification Transparent](https://no-cache.hubspot.com/cta/default/3893111/93e4d869-8de4-4ffd-8aad-33538c5ce0ee.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/93e4d869-8de4-4ffd-8aad-33538c5ce0ee)*

[Moh Heng Goh](https://blog.bcm-institute.org/cm-v2/author/moh-heng-goh) Nov 25, 2026

## [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/8ed24986-bf49-4aa4-865f-0c93142fa991.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/8ed24986-bf49-4aa4-865f-0c93142fa991)

## **eBook 3 \[CORE\]: Chapter 5**

## [![\[CM\] \[E3\] \[C1\] Starting Your CM Implementation Banner](https://no-cache.hubspot.com/cta/default/3893111/1bf08c12-b11b-44cc-a7a5-3bd25c740d4c.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/1bf08c12-b11b-44cc-a7a5-3bd25c740d4c)

 **Treatment and Control for Jamiyah Home for the Aged** 

## Introduction

[![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/422eee8a-7fb9-446e-8f52-c29f5ebcf795.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/422eee8a-7fb9-446e-8f52-c29f5ebcf795)[![\[CM\] \[JHA\] \[E3\] \[C4\] \[CRA\] \[2-1\] Treatment and Control](https://no-cache.hubspot.com/cta/default/3893111/1dd2b947-c883-4c8d-9d48-575a0866b469.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/1dd2b947-c883-4c8d-9d48-575a0866b469)Once the threats are listed, the next question is what Jamiyah Home for the Aged (JHA) already does about each one, and what more it should do. This chapter, Crisis Scenario Risk Assessment (CRA) Part 2, records the treatment and control for every threat from Chapters 2 and 4.

It covers all 22 threats. For each one, it shows the four treatment options, the controls believed to exist, and the controls planned.

*Every rating, control, strategy, and time target in this chapter is a proposed draft built from public information about JHA and must be validated by JHA before use.*

## The Four Risk Treatment Options

Every risk can be treated in one or more of four ways. The working definitions below are used throughout the table.

- **Risk avoidance:** stopping the activity or condition that creates the risk, where this is possible without harming the mission of the home.
- **Risk reduction:** lowering the likelihood or impact through measures such as maintenance, training, backups, and drills.
- **Risk transference:** moving some or all of the financial or operational burden to another party, such as an insurer or a contractor.
- **Risk acceptance:** deciding knowingly to live with a risk, usually because it is small or the cost of treatment is too high.

For a home that cares for frail residents, acceptance should be used with care. Risks to life are never accepted. Only small, short and well-understood events fall into this category.

## Existing and Planned Controls

Existing controls are the measures already in place. The public website says very little about them, so most entries are marked "to be confirmed by JHA". Where an entry says "typical requirement", it refers to something that a licensed home would normally have, but which the home must confirm. Planned controls are the additional measures proposed to bring the risk to an acceptable level.

**Table 5.1: Treatment and control for Jamiyah Home for the Aged**

| **Type of Threats / Crisis Scenario** | **Existing Risk Treatment - Risk Avoidance** | **Existing Risk Treatment - Risk Reduction** | **Existing Risk Treatment - Risk Transference** | **Existing Risk Treatment - Risk Acceptance** | **Existing Controls** | **Additional (Planned) Controls** |
| --- | --- | --- | --- | --- | --- | --- |
| **T01 Flash flood** | **Not possible to avoid the weather; avoid keeping critical stock and records at floor level.** | **Raise stock off the floor, check drains before the monsoon season and brief staff on alternative routes.** | **Property and business interruption insurance (cover to be confirmed).** | **Accept road closures that last only a few hours.** | **Routine drain and roof maintenance; duty roster for call-in (to be confirmed by JHA).** | **Flood response checklist; alternative access routes; emergency stock held on an upper level.** |
| **T02 Haze** | **Not possible to avoid; avoid outdoor activities on poor air days.** | **Monitor air quality, keep windows closed, stock masks and air purifiers and keep rescue medication available.** | **None practical for the haze itself; review resident medical insurance arrangements.** | **Accept cancellation of outdoor programmes.** | **Activities can be moved indoors (to be confirmed by JHA).** | **Haze protocol linked to national air quality bands; purchase of air purifiers.** |
| **T03 Extreme heat** | **Avoid strenuous activity in the hottest hours.** | **Maintain fans and air-conditioning, run hydration rounds, use light clothing and monitor vital signs.** | **Equipment warranties and maintenance contracts for cooling units.** | **Accept occasional discomfort that is managed by routine care.** | **Hydration routines during daily care (to be confirmed by JHA).** | **Heat plan with trigger temperatures; a cooled common room.** |
| **T04 Storm and lightning** | **Not possible to avoid; keep residents away from windows during storms.** | **Prune trees, test lightning protection and fit surge protectors on key equipment.** | **Property insurance.** | **Accept minor leaks that can be repaired quickly.** | **Building maintenance programme (to be confirmed by JHA).** | **Storm warning protocol; yearly test of lightning protection.** |
| **T05 Fire** | **Ban open flames and unsafe heaters; avoid overloaded sockets.** | **Fire detection, extinguishers, evacuation aids, regular drills (including night-shift drills), and electrical inspections.** | **Fire and public liability insurance.** | **Accept only small contained incidents that staff can handle; never accept risk to life.** | **Statutory fire safety arrangements and drills (to be confirmed by JHA).** | **Horizontal evacuation plan; more evacuation aids; a drill that tests night staffing.** |
| **T06 Bomb threat or security incident** | **Control entry to the building.** | **Visitor registration, security briefing, and lockdown and evacuation procedures.** | **Public liability insurance.** | **Accept very low likelihood threats that are handled by the police.** | **Visitors must write to the Superintendent before visiting (stated on the JHA website).** | **Lockdown procedure; contact route to the police; staff briefing.** |
| **T07 Unsafe building or structural defect** | **Do not defer maintenance of structure, roof and services.** | **Periodic inspection and preventive maintenance.** | **Property insurance and contractor warranties.** | **Accept minor repairs that do not affect residents.** | **Building maintenance (to be confirmed by JHA).** | **Building condition audit; relocation arrangement with other Jamiyah homes (assumed, to be agreed).** |
| **T08 Infectious disease outbreak** | **Cannot be avoided; avoid risk by screening visitors and excluding sick staff.** | **Vaccination, hand hygiene, infection control training, isolation rooms and visitor controls.** | **Limited; outbreak response costs are not usually insurable.** | **Accept mild seasonal illness managed by routine care.** | **Visitors write to the Superintendent first (website); routine infection control (to be confirmed by JHA).** | **Outbreak playbook; cohort zones; protective equipment stock; staff vaccination drive.** |
| **T09 Shortage of care staff** | **Avoid tasks that only one person can do.** | **Cross-training, a flexible roster, an agency and volunteer pool and a retention programme.** | **Contract with a staffing agency for urgent cover.** | **Accept a temporary cut in non-essential activities.** | **Shift roster and duty manager system (to be confirmed by JHA).** | **Minimum safe staffing table; call-in tree; standing agreement with an agency.** |
| **T10 Foodborne illness cluster** | **Do not serve high-risk food items to residents.** | **Kitchen hygiene, temperature control, supplier checks and retained food samples.** | **Supplier contract indemnities and liability insurance.** | **Accept isolated mild stomach upsets.** | **Kitchen hygiene practice (to be confirmed by JHA).** | **Food safety audit; retained sample procedure; outbreak reporting steps.** |
| **T11 Medication and medical supply interruption** | **Avoid reliance on a single supplier.** | **Minimum stock levels, a second supplier and a monthly stock check.** | **Supply contract with service levels and penalties.** | **Accept brand substitution when the doctor approves it.** | **Regular ordering routine (to be confirmed by JHA).** | **A buffer stock of critical items; list of backup suppliers.** |
| **T12 Food and catering disruption** | **Avoid a single food source.** | **A three-day emergency food stock that covers special diets, and a backup caterer.** | **Contract penalties for missed deliveries.** | **Accept a temporary simpler menu.** | **Kitchen arrangements (to be confirmed by JHA).** | **Emergency menu; alternative kitchen arrangements.** |
| **T13 Outsourced service provider failure** | **Choose financially sound vendors.** | **Contract clauses on continuity, backup vendors and an in-house minimum service.** | **Service level agreements.** | **Accept short delays in non-critical services.** | **Contractor management (to be confirmed by JHA).** | **Register of critical vendors with backup contacts.** |
| **T14 Power outage** | **Cannot be avoided; avoid dependence on one power source.** | **A backup generator or battery units, uninterruptible power supply for key devices and regular testing.** | **Property and business interruption insurance.** | **Accept very short power dips.** | **Emergency lighting (typical requirement; to be confirmed by JHA).** | **Generator test schedule; list of priority loads; battery packs for oxygen devices.** |
| **T15 Lift or hoist failure** | **Place residents who cannot walk on the ground floor where possible.** | **Preventive maintenance contract, manual evacuation aids and spare slings.** | **Maintenance contract with a response time.** | **Accept short downtime when stairs are not needed.** | **Lift maintenance contract (to be confirmed by JHA).** | **Priority repair clause; evacuation chair training.** |
| **T16 Water supply interruption** | **Cannot be avoided.** | **Stored water, bottled water stock, and a hygiene plan.** | **Property insurance.** | **Accept shortcuts.** | **Routine plumbing maintenance (to be confirmed by JHA).** | **Emergency water stock; supplier for tanker water.** |
| **T17 Ransomware attack** | **Do not open untrusted attachments or links.** | **Offline backups, software updates, multi-factor sign-in and staff training.** | **Cyber insurance.** | **Accept low-level phishing attempts that are blocked.** | **Basic antivirus and backups (to be confirmed by JHA).** | **Tested restore; paper fallback forms for medication and care notes.** |
| **T18 Loss of information systems** | **Avoid systems that cannot be recovered.** | **Vendor service levels, daily backups and paper downtime forms.** | **Vendor contract with recovery terms.** | **Accept minor outages that last under an hour.** | **Backups (to be confirmed by JHA).** | **Recovery time targets for each system; downtime form pack.** |
| **T19 Telecommunication or internet outage** | **Avoid a single provider.** | **Mobile phones as backup, a second internet line and printed contact lists.** | **Service level agreement with the provider.** | **Accept short outages.** | **Mobile phones held by managers (to be confirmed by JHA).** | **Second line; offline contact book.** |
| **T20 Failure of medical equipment** | **Do not use equipment past its service date.** | **Preventive maintenance, spare units and battery checks.** | **Warranties and service contracts.** | **Accept failures of non-critical equipment.** | **Equipment servicing (to be confirmed by JHA).** | **Spare oxygen units; asset register with service dates.** |
| **T21 Personal data breach** | **Collect only the data that is needed.** | **Access control, encryption, staff training and a clean desk rule.** | **Cyber insurance.** | **Accept low-risk errors that are corrected at once.** | **Confidentiality practice (to be confirmed by JHA).** | **Breach response steps; data protection officer role; yearly training.** |
| **T22 Nurse call and alarm system failure** | **Avoid single points of failure in the alarm network.** | **Preventive maintenance, backup handheld bells and regular rounds.** | **Maintenance contract with a response time.** | **Accept very short faults in a single room.** | **Maintenance contract (to be confirmed by JHA).** | **Weekly test; handheld bells; round schedule for outages.** |

## Reading Across the Table

Three patterns appear in the table. First, risk reduction is the main option for almost every threat, since most threats cannot be avoided or passed to someone else. Second, transference is mainly financial. Insurance and contracts can pay for damage, but they cannot protect a resident during a fire or an outage. Third, the planned controls often include a plan, a test or a stock level, which are cheap compared with the harm they prevent.

The table also shows where the home will need budget. Items such as backup power, evacuation aids, an agency staffing agreement, and a protective equipment stock need approval, and the JHA board should review them with the risk ratings from Chapter 6.

## Next Steps

1. Confirm every entry marked "to be confirmed" and replace it with the actual control.
2. Name an owner and a date for each planned control.
3. Test the controls with a drill or a check, and record the result.
4. Update the table after each incident, audit or exercise.

## [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/bad7a111-1867-45a8-8fc3-ce1000eed090.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/bad7a111-1867-45a8-8fc3-ce1000eed090)

## Conclusion

The treatment and control table shows what JHA has, what it needs and where the gaps lie. It turns a list of worries into a list of actions. The next chapter scores each threat for impact and likelihood so the actions can be prioritised.

Ready to build your own crisis management capability? Explore the Business Continuity Management (BCM) Institute certification and competency-based courses at [https://blog.bcm-institute.org/certification](https://blog.bcm-institute.org/certification).

[![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/9191b129-a00c-431b-aafc-908f8e6bc381.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/9191b129-a00c-431b-aafc-908f8e6bc381)

| **eBook 3: Starting Your Crisis Management Implementation** |  |  |  |
| --- | --- | --- | --- |
| **\[E3\] \[C1\]** | **\[CRA\] \[1-1\]** | **\[CRA\] \[1-2\]** | **\[CRA\] \[1-3\]** |
| [![\[CM\] \[JHA\] \[E3\] \[C1\] \[CORE\] Starting Your CM Implementation](https://no-cache.hubspot.com/cta/default/3893111/cff5031d-9399-40a7-a94f-15f3fcf90de5.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/cff5031d-9399-40a7-a94f-15f3fcf90de5) | [![\[CM\] \[JHA\] \[E3\] \[C2\] \[CRA\] \[1-1\] List of Threats](https://no-cache.hubspot.com/cta/default/3893111/facc69ed-cf89-4ba5-8d65-1145d8d00fa4.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/facc69ed-cf89-4ba5-8d65-1145d8d00fa4) | [![\[CM\] \[JHA\] \[E3\] \[C3\] \[CRA\] \[1-2\] List of Crisis Scenarios](https://no-cache.hubspot.com/cta/default/3893111/8f7b8553-57c2-44fe-b1d9-660cfe8828cb.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/8f7b8553-57c2-44fe-b1d9-660cfe8828cb) | [![\[CM\] \[JHA\] \[E3\] \[C3\] \[CRA\] \[1-3\] List of Technology Threats](https://no-cache.hubspot.com/cta/default/3893111/674b4730-fce3-4375-a83c-1c5314dbb95b.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/674b4730-fce3-4375-a83c-1c5314dbb95b) |
| **\[CRA\] \[2-1\]** | **\[CRA\] \[2-2\]** | **\[CMS\] \[3-1\]** | **\[CMS\] \[3-2\]** |
| [![\[CM\] \[JHA\] \[E3\] \[C4\] \[CRA\] \[2-1\] Treatment and Control](https://no-cache.hubspot.com/cta/default/3893111/1dd2b947-c883-4c8d-9d48-575a0866b469.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/1dd2b947-c883-4c8d-9d48-575a0866b469) | [![\[CM\] \[JHA\] \[E3\] \[C5\] \[CRA\] \[2-2\] Crisis Risk Impact and Likelihood Assessment](https://no-cache.hubspot.com/cta/default/3893111/6866981a-d0d7-4f22-8767-c93025af0288.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/6866981a-d0d7-4f22-8767-c93025af0288) | [![\[CM\] \[JHA\] \[E3\] \[C6\] \[CMS\] \[3-1\] Crisis Prevention Strategy](https://no-cache.hubspot.com/cta/default/3893111/40635507-99f4-4cfe-9ec2-d682553cbec4.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/40635507-99f4-4cfe-9ec2-d682553cbec4) | [![\[CM\] \[JHA\] \[E3\] \[C7\] \[CMS\] \[3-2\] Crisis Response Strategy](https://no-cache.hubspot.com/cta/default/3893111/36d9a840-db77-4682-a69d-a7110060562f.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/36d9a840-db77-4682-a69d-a7110060562f) |

More Information About Crisis Management Blended/ Hybrid Learning Courses

To learn more about the course and schedule, click the buttons below for CM-300 Crisis Management Implementer \[CM-3\] and CM-5000 Crisis Management Expert Implementer \[CM-5\].

| [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/5ffecd2d-8000-4805-b5e3-e9ead2e259cc.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/5ffecd2d-8000-4805-b5e3-e9ead2e259cc) | [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/c3546220-6c76-4a10-8c76-4040b94e09e5.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/c3546220-6c76-4a10-8c76-4040b94e09e5) | [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/03294547-1df3-435c-9243-971c3d9bb6ce.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/03294547-1df3-435c-9243-971c3d9bb6ce) |
| --- | --- | --- |
| [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/b29594fe-d44a-4ff8-8160-03f7ce454385.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/b29594fe-d44a-4ff8-8160-03f7ce454385) | [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/dd120e7f-9fe2-49ed-ad24-489b81c06739.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/dd120e7f-9fe2-49ed-ad24-489b81c06739) | [![\[BL-CM\] \[5\] Register](https://no-cache.hubspot.com/cta/default/3893111/82024308-16f4-4491-98be-818a882c6286.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/82024308-16f4-4491-98be-818a882c6286) |
| [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/c8aaf76b-4c0b-402a-ad12-c8aff24eb911.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/c8aaf76b-4c0b-402a-ad12-c8aff24eb911) | Please feel free to send us a note if you have any questions. [![Email to Sales Team \[BCM Institute\]](https://no-cache.hubspot.com/cta/default/3893111/3c53daeb-2836-4843-b0e0-645baee2ab9e.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/3c53daeb-2836-4843-b0e0-645baee2ab9e) | [![FAQ BL-CM-5 CM-5000](https://no-cache.hubspot.com/cta/default/3893111/30bcbbbf-c8ea-48d8-8643-da2638f3f0f8.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/30bcbbbf-c8ea-48d8-8643-da2638f3f0f8) |
| [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/83d00c12-c51c-4476-9902-69f9b7667a91.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/83d00c12-c51c-4476-9902-69f9b7667a91) | [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/672d2949-6233-4b26-ad42-ae0dd0a1a3ac.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/672d2949-6233-4b26-ad42-ae0dd0a1a3ac) | [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/3ca6f50d-a3c5-41b8-8da2-26feb8a7613e.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/3ca6f50d-a3c5-41b8-8da2-26feb8a7613e) |

 

 

## **Comments**

![CTA Banner\_OR](https://blog.bcm-institute.org/hubfs/CTA%20Banner%20for%20Blog/CTA%20Banner_OR.jpg "CTA Banner_OR")

---

![CTA Banner\_ORA](https://blog.bcm-institute.org/hubfs/CTA%20Banner%20for%20Blog/CTA%20Banner_ORA.jpg "CTA Banner_ORA")

---

![CTA Banner\_BCM](https://blog.bcm-institute.org/hubfs/CTA%20Banner%20for%20Blog/CTA%20Banner_BCM.jpg "CTA Banner_BCM")

---

![CTA Banner\_ITDR](https://blog.bcm-institute.org/hubfs/CTA%20Banner%20for%20Blog/CTA%20Banner_ITDR.jpg "CTA Banner_ITDR")

---

![CTA Banner\_CM](https://blog.bcm-institute.org/hubfs/CTA%20Banner%20for%20Blog/CTA%20Banner_CM.jpg "CTA Banner_CM")

![BCMIWhiteLogoSmall.png](https://blog.bcm-institute.org/hs-fs/hubfs/Blog%20Testing/BCMIWhiteLogoSmall.png?width=72&name=BCMIWhiteLogoSmall.png "BCMIWhiteLogoSmall.png")

All rights reserved. Copyright 2026

```json
{
  "@context" : "https://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "Moh Heng Goh",
    "url" : "https://blog.bcm-institute.org/cm-v2/author/moh-heng-goh"
  },
  "dateModified" : "2026-11-25T08:33:37.064Z",
  "datePublished" : "2026-11-25T08:23:52.000Z",
  "headline" : "[CM] [JHA] [E3] [CORE] Chapter 5: Treatment and Control for Jamiyah Home for the Aged",
  "image" : [ "https://blog.bcm-institute.org/hubfs/JHA%20Graphic%20Folder/JHA%20CM%20Morepost/JHA%20CM%20E3%20Morepost/%5BCM%5D%20%5BJHA%5D%20%5BE3%5D%20%5BC4%5D%20%5BCRA%5D%20%5B1-3%5D%20Treatment%20and%20Control.png" ],
  "mainEntityOfPage" : {
    "@id" : "https://blog.bcm-institute.org/cm-v2/cm-jha-e3-core-chapter-5-treatment-and-control-for-jamiyah-home-for-the-aged",
    "@type" : "WebPage"
  },
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "url" : "https://blog.bcm-institute.org/hubfs/BCMI%20Logo.png"
    },
    "name" : "BCMI Pte Ltd"
  }
}
```