title: "[BCM] [EGH] [E2] [C2] Project Management Phase for Business Continuity Management Planning Methodology for Eastern General Hospital"
description: "Chapter 2 covers the Project Management phase of EGH's ISO 22301 BCM planning: scope, sponsor, steering committee, responsibility matrix, risks and handover."
---

.

[![BCMIWhiteLogo.png](https://blog.bcm-institute.org/hs-fs/hubfs/Blog%20Testing/BCMIWhiteLogo.png?width=556&name=BCMIWhiteLogo.png "BCMIWhiteLogo.png")](http://www.bcm-institute.org/)

- [Home](https://www.bcm-institute.org/)
- [About Us](https://www.bcm-institute.org/about-us-3/) 
    - [A President’s Perspective](https://www.bcm-institute.org/about-us/a-presidents-perspective/)
    - [Our History](https://www.bcm-institute.org/about-us/our-history/)
    - [Our Advisory Council](https://www.bcm-institute.org/about-us/our-advisory-council/)
    - [Customers’ Testimonials](https://www.bcm-institute.org/about-us/customers-testimonials/)
    - [Credential Verification](https://www.bcm-institute.org/about-us/credential-verification/)
- [Courses](https://blog.bcm-institute.org/blog/course-fees-for-blended-learning-courses-master-catalog) 
    - [ISO 22301 Business Continuity Management System Audit](https://blog.bcm-institute.org/audit/business-continuity-management-audit-courses)
    - [ISO 22301 Business Continuity Management](https://blog.bcm-institute.org/bcm/business-continuity-management-courses)
    - [Crisis Communication](https://blog.bcm-institute.org/crisis-communication/crisis-communication-courses)
    - [Crisis Management](https://blog.bcm-institute.org/en/crisis-management/courses)
    - [IT Disaster Recovery](https://blog.bcm-institute.org/it-disaster-recovery/courses)
    - [Operational Resilience](https://blog.bcm-institute.org/operational-resilience/courses)
    - [Operational Resilience Audit](https://blog.bcm-institute.org/operational-resilience-audit/courses)
- [Certification](https://blog.bcm-institute.org/certification/types-of-certifications-offered) 
    - [ISO 22301 BCMS Audit Certification](https://blog.bcm-institute.org/certification/business-continuity-management-audit-certification)
    - [ISO22301 Business Continuity Management Certification](https://blog.bcm-institute.org/bcm/business-continuity-management-certification)
    - [Crisis Communication Certification](https://blog.bcm-institute.org/crisis-communication/crisis-communication-certification)
    - [Crisis Management Certification](https://blog.bcm-institute.org/en/crisis-management/crisis-management-certification)
    - [IT Disaster Recovery Planning Certification](https://blog.bcm-institute.org/it-disaster-recovery/it-disaster-recovery-certification)
    - [Operational Resilience Certification](https://blog.bcm-institute.org/operational-resilience/operational-resilience-certification)
    - [Operational Resilience Audit Certification](https://blog.bcm-institute.org/operational-resilience-audit)
- [Seminars](https://blog.bcm-institute.org/meet-the-expert/mte-webinar-mainpage)
- [Store](https://www.bcm-institute.org/store-2/)
- [Contact Us](http://www.bcm-institute.org/about-us/contact-us/)

- <https://www.facebook.com/BCMInstitute/>
- <https://www.linkedin.com/company/business-continuity-management-institute-bcm-institute>

###### Keeping Care Running: Managing and Implementing Business Continuity Management at Eastern General Hospital

![CC Ai Gen\_with Cert Logo 1](https://blog.bcm-institute.org/hs-fs/hubfs/BB%20CC%20%5BAi%20Gen%20Blog%20Photo%5D/CC%20Ai%20Gen_with%20Cert%20Logo%201.jpg?width=3000&height=2000&name=CC%20Ai%20Gen_with%20Cert%20Logo%201.jpg "CC Ai Gen_with Cert Logo 1")

# \[BCM\] \[EGH\] \[E2\] \[C2\] Project Management Phase for Business Continuity Management Planning Methodology for Eastern General Hospital

[![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/dfa53785-5be1-4117-a1bc-43e40cdb42e8.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/dfa53785-5be1-4117-a1bc-43e40cdb42e8)

The first phase of the methodology, Project Management (PM), decides whether the rest of the work will have authority, people and time. For Eastern General Hospital (EGH), whose [official website](https://www.egh.com.sg/) describes an upcoming acute hospital of about 1,000 beds, a good project set-up also means tying continuity work to a building and service programme that is still moving.

[Moh Heng Goh](https://blog.bcm-institute.org/bcm-v2/author/moh-heng-goh) Nov 17, 2026

#### [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/c5748bd7-2a18-4a78-8cc9-7dcc65204af9.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/c5748bd7-2a18-4a78-8cc9-7dcc65204af9)

## [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/f3c50f04-ebe4-4e72-a7cf-10ee0040d496.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/f3c50f04-ebe4-4e72-a7cf-10ee0040d496)

## Introduction

The first phase of the methodology, Project Management (PM), decides whether the rest of the work will have authority, people and time. For Eastern General Hospital (EGH), whose [official website](https://www.egh.com.sg/) describes an upcoming acute hospital of about 1,000 beds, a good project set-up also means tying continuity work to a building and service programme that is still moving.

This chapter explains scope and objectives, the sponsor, the steering committee and project team (with a responsibility matrix), planning of the work, project risks and communication, resources and standards, and the handover from project to routine programme management. All names, roles, dates and figures are illustrative and should be confirmed by EGH.

## Scope and Objectives

Scope states what the BCM project covers and what it leaves out. For EGH, a sensible starting scope is the acute hospital service and the services that support it, namely emergency, inpatient and outpatient care, virtual and home-based care, and the clinical and facilities functions listed in Chapter 4. The planned Eastern Community Hospital (ECH), run by SingHealth Community Hospitals, would sit at the boundary: its beds are a dependency for patient flow, but its own continuity arrangements belong to its operator. Interfaces with it should be recorded rather than assumed.

Objectives should be few and measurable. For example, EGH might set these objectives:

- Agree a set of critical business functions, with recovery times, before the first physical service opens.
- Complete a validated business continuity plan for every Tier 1 function (ten of the sixteen functions in Chapter 4) before that function goes live.
- Run at least one walkthrough exercise for each opening stage.
- Hand over to a standing programme owner by an agreed date.

Exclusions matter as much. If, for example, long-term disaster recovery of the construction programme is outside scope, the charter should say so, so that nobody assumes it is covered.

## The Sponsor

A sponsor is a senior executive who owns the outcome, secures resources and removes obstacles. The sponsor must have enough standing to challenge clinical and corporate departments alike. In a hospital this might be the chief executive officer or a deputy with authority across clinical services and operations. The sponsor approves the charter, chairs or attends the steering committee, and signs off the plans in Chapter 6. A project without a visible sponsor typically finds that business units treat BCM requests as optional.

## Steering Committee and Project Team

The steering committee provides direction and approves major decisions. For EGH it might include the sponsor, a senior clinician from the emergency and critical care areas, the head of nursing, the heads of facilities and of information technology, and the commissioning and design leads. The presence of commissioning and design leads reflects the pre-opening lens introduced in Chapter 1: decisions about utilities, layout and network paths are made during design, and continuity requirements must reach the people making them.

The project team does the work. It is led by a project manager, usually the organisation BCM coordinator, supported by business unit BCM coordinators nominated from each clinical and support area, and by specialists in risk, infrastructure, information security and communications. Business unit coordinators are the main link to the people who will write and use plans, so their time must be agreed with their line managers at the start.

### Responsibility Matrix

A responsibility matrix removes doubt about who decides, who does, who is consulted and who is informed. The table below is an illustrative example using the codes R (responsible), A (accountable), C (consulted) and I (informed).

| **Activity** | **Sponsor** | **Steering committee** | **Project manager** | **Business unit coordinators** | **Specialists** |
| --- | --- | --- | --- | --- | --- |
| **Approve charter and scope** | **A** | **R** | **C** | **I** | **I** |
| **Maintain risk register (R1 to R10)** | **I** | **A** | **R** | **C** | **R** |
| **Conduct business impact analysis** | **I** | **A** | **R** | **R** | **C** |
| **Choose strategies** | **A** | **R** | **R** | **C** | **C** |
| **Write and validate plans** | **I** | **A** | **C** | **R** | **C** |
| **Plan and run exercises** | **I** | **A** | **R** | **R** | **C** |
| **Report progress** | **I** | **I** | **R** | **C** | **I** |

## Planning the Work

The work plan breaks the project into tasks, owners, dependencies and dates. Four practical rules help:

1. **Work back from fixed dates.** Because EGH has opening milestones, the plan should start from them. A function that opens in a given stage needs its impact analysis, strategy and plan ready before that stage, not after.
2. **Sequence by tier.** Tier 1 functions, which in the illustrative ranking in Chapter 4 have a recovery time of four hours or less, should be analysed and planned first.
3. **Build in review points.** Each phase ends with a checkpoint at which the steering committee accepts the output before the next phase begins.
4. **Allow for clinical time.** Clinicians have limited hours outside patient care. Workshops should be short, scheduled early and run at times that suit rosters.

## Project Risks and Communication

The project itself can fail, so it needs its own small risk list, kept apart from the operational register in Chapter 3. Typical project risks are listed below, each with a possible response.

- **Competing priorities during opening:** agree protected time and escalate through the sponsor.
- **Changes to the opening schedule:** link the plan to the commissioning timetable and review at every change.
- **Turnover of coordinators:** name deputies and keep handover notes.
- **Inconsistent data:** use one template for the impact analysis and one owner for the master list of functions.

Communication keeps the project visible. A short monthly report to the steering committee, a standing item at department head meetings and a single contact point for questions are usually enough. Reports should show progress against the plan, decisions needed and risks to the project, and should avoid technical detail that readers cannot act on.

Escalation paths should also be agreed at the start. A business unit coordinator who cannot obtain a manager's time should know that the issue goes first to the project manager, then to the steering committee chair, and finally to the sponsor, within set periods such as five working days for each step. Recording these steps in the charter turns a possible dispute into a routine decision, and it shows department heads that the sponsor expects continuity work to be completed on schedule. Decisions taken at steering committee meetings should be minuted with an owner and a date, and the minutes should be circulated within two working days so that actions are not lost between meetings.

## Resources and Standards

Resources include people's time, a modest budget for workshops and exercise logistics, a shared repository for documents and, later, a notification tool for call trees. The main standard is ISO 22301, which sets requirements for a business continuity management system, with its companion guidance on implementation. In Singapore, hospital services are also bound by the Healthcare Services Act 2020 and its regulations, so the project should keep a simple register of the legal and licensing requirements that touch continuity, and review it when MOH issues new circulars or licence conditions. Chapter 7 reports what was found on exercising requirements.

## Requirements Specific to EGH

Three requirements follow from EGH's position as an upcoming hospital and part of the SingHealth group.

- **Staged opening.** The project must be able to report continuity readiness for each stage, starting with the virtual service planned for 2026 and ending with the physical campus due in 2029 to 2030, according to the hospital's website.
- **Group alignment.** EGH is part of the One SingHealth network and collaborates with national specialty centres. The project should find out which group-level policies, incident arrangements or templates already exist, and adopt them where they fit rather than create parallel versions. Whether such arrangements exist has not been confirmed in this eBook.
- **Shared campus.** Interfaces with Eastern Community Hospital should be written down, including who calls whom when a patient transfer is blocked.

## Handover to Programme Management

A project ends, but continuity does not. The final project task is a formal handover to a standing owner, typically the organisation BCM coordinator reporting to a BCM steering group, who runs the programme described in Chapter 8. The handover pack should include the approved charter, the risk register, the impact analysis, the strategies, the validated plans, exercise results, the open actions and the review calendar. The steering committee should record its acceptance of the pack, and the sponsor should confirm funding for the first year of programme activity.

## Summary Table

| **Element** | **What to settle** | **Illustrative EGH example** |
| --- | --- | --- |
| **Scope** | **Services covered and excluded** | **Acute hospital service and supporting functions; ECH as an interface** |
| **Objectives** | **Measurable results and dates** | **Plans for all Tier 1 functions before go-live** |
| **Sponsor** | **Senior owner of the outcome** | **Chief executive officer or deputy** |
| **Steering committee** | **Direction and approvals** | **Clinical, nursing, facilities, IT, commissioning leads** |
| **Project team** | **Delivery of the work** | **Organisation coordinator plus business unit coordinators** |
| **Work plan** | **Tasks, owners, dates** | **Worked back from opening milestones** |
| **Project risks** | **Threats to the project** | **Opening pressure, coordinator turnover** |
| **Handover** | **Transfer to standing programme** | **Pack accepted by steering committee** |

## [![New call-to-action](https://no-cache.hubspot.com/cta/default/3893111/297a5452-5a0d-4b73-9778-093a77c00efb.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/297a5452-5a0d-4b73-9778-093a77c00efb)

Project Management gives the later phases their authority. A named sponsor, a committee that includes design and commissioning leads, a clear responsibility matrix and a plan worked back from opening dates allow EGH to build continuity into the hospital while it is still taking shape. The next phase, Risk Analysis and Review, uses this structure to identify what could disrupt the services in scope.

## Sources

- [Eastern General Hospital, Hospital Overview](https://www.egh.com.sg/about-egh/hospital-overview/).
- [HCSA, Summary of requirements for licensees](https://www.hcsa.gov.sg/about-us/2-summary-of-requirements/).

**Continue reading:** Chapter 3, *Risk Analysis and Review Phase for Business Continuity Management Planning Methodology for Eastern General Hospital*, which shows how to identify, score and reduce the risks, using a register of ten risks coded R1 to R10.

 

| Keeping Care Running: Managing and Implementing Business Continuity Management at Eastern General Hospital |  |  |  |  |
| --- | --- | --- | --- | --- |
| **eBook 2: Implementing Business Continuity Management** |  |  |  |  |
| **C1** | **C2** | **C3** | **C4** | **C5** |
| [![\[BCM\] \[EGH\] \[E2\] \[C1\] Business Continuity Management Planning Methodology](https://no-cache.hubspot.com/cta/default/3893111/ae929f9f-d9ce-4159-89d6-7e4e808e302e.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/ae929f9f-d9ce-4159-89d6-7e4e808e302e) | [![\[BCM\] \[EGH\] \[E2\] \[C2\] Project Management](https://no-cache.hubspot.com/cta/default/3893111/31402f15-220b-47f2-96bd-c1c0b99f601b.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/31402f15-220b-47f2-96bd-c1c0b99f601b) | [![\[BCM\] \[EGH\] \[E2\] \[C3\] Risk Analysis and Review](https://no-cache.hubspot.com/cta/default/3893111/47b1732f-7d2d-4b7f-9e2c-1bb9f5eb37e9.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/47b1732f-7d2d-4b7f-9e2c-1bb9f5eb37e9) | [![\[BCM\] \[EGH\] \[E2\] \[C4\] Business Impact Analysis](https://no-cache.hubspot.com/cta/default/3893111/354c4374-6f93-47df-8e52-f9cae94c431c.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/354c4374-6f93-47df-8e52-f9cae94c431c) | [![\[BCM\] \[EGH\] \[E2\] \[C5\] Business Continuity Strategy](https://no-cache.hubspot.com/cta/default/3893111/883a28c8-785a-42c1-bec1-ab356f5dfe62.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/883a28c8-785a-42c1-bec1-ab356f5dfe62) |
| **C6** | **C7** | **C8** | **C9** | **C10** |
| [![\[BCM\] \[EGH\] \[E2\] \[C6\] BCM Plan Development](https://no-cache.hubspot.com/cta/default/3893111/c706799d-aeab-4a5e-89c0-3aa51b17707c.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/c706799d-aeab-4a5e-89c0-3aa51b17707c) | [![\[BCM\] \[EGH\] \[E2\] \[C7\] Testing and Exercising](https://no-cache.hubspot.com/cta/default/3893111/4bebd8de-6b61-4578-b24a-3ceb6a11cd05.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/4bebd8de-6b61-4578-b24a-3ceb6a11cd05) | [![\[BCM\] \[EGH\] \[E2\] \[C8\] Program Management](https://no-cache.hubspot.com/cta/default/3893111/d7d1ea36-1913-4593-8189-04e6d1b116d7.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/d7d1ea36-1913-4593-8189-04e6d1b116d7) | [![\[BCM\] \[EGH\] \[E2\] \[C9\] Summary](https://no-cache.hubspot.com/cta/default/3893111/0829428d-9f00-473a-8c9e-f138e9c32798.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/0829428d-9f00-473a-8c9e-f138e9c32798) | [![\[BCM\] \[EGH\] \[E2\] \[C10\] Back Cover](https://no-cache.hubspot.com/cta/default/3893111/a8ed064d-96cf-41d5-b4d9-c2ef1f77a7a6.png)](https://cta-redirect.hubspot.com/cta/redirect/3893111/a8ed064d-96cf-41d5-b4d9-c2ef1f77a7a6) |
|  |  |  |  |  |

---

## **Comments**

![CTA Banner\_OR](https://blog.bcm-institute.org/hubfs/CTA%20Banner%20for%20Blog/CTA%20Banner_OR.jpg "CTA Banner_OR")

---

![CTA Banner\_ORA](https://blog.bcm-institute.org/hubfs/CTA%20Banner%20for%20Blog/CTA%20Banner_ORA.jpg "CTA Banner_ORA")

---

![CTA Banner\_BCM](https://blog.bcm-institute.org/hubfs/CTA%20Banner%20for%20Blog/CTA%20Banner_BCM.jpg "CTA Banner_BCM")

---

![CTA Banner\_ITDR](https://blog.bcm-institute.org/hubfs/CTA%20Banner%20for%20Blog/CTA%20Banner_ITDR.jpg "CTA Banner_ITDR")

---

![CTA Banner\_CM](https://blog.bcm-institute.org/hubfs/CTA%20Banner%20for%20Blog/CTA%20Banner_CM.jpg "CTA Banner_CM")

![BCMIWhiteLogoSmall.png](https://blog.bcm-institute.org/hs-fs/hubfs/Blog%20Testing/BCMIWhiteLogoSmall.png?width=72&name=BCMIWhiteLogoSmall.png "BCMIWhiteLogoSmall.png")

All rights reserved. Copyright 2026

```json
{
  "@context" : "https://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "Moh Heng Goh",
    "url" : "https://blog.bcm-institute.org/bcm-v2/author/moh-heng-goh"
  },
  "dateModified" : "2026-11-17T05:20:48.103Z",
  "datePublished" : "2026-11-17T05:17:53.000Z",
  "headline" : "[BCM] [EGH] [E2] [C2] Project Management Phase for Business Continuity Management Planning Methodology for Eastern General Hospital",
  "mainEntityOfPage" : {
    "@id" : "https://blog.bcm-institute.org/bcm-v2/bcm-egh-e2-c2-project-management-phase-for-business-continuity-management-planning-methodology-for-eastern-general-hospital",
    "@type" : "WebPage"
  },